Your project requires the settlement of a condition contract in SAP S/4HANA.Which of the following settlement types can you use? Choose Three correct answers.

Your project requires the settlement of a condition contract in SAP S/4HANA.Which of the following settlement types can you use? Choose Three correct answers.

A. Periodic settlement

B. Final settlement

C. Delta settlement

D. Invoice settlement

Answer: A,B,C