Your organization has a defined portfolio management process that it has followed for three years. As the portfolio manager, you keep your various plans up to date, and because of numerous regulatory changes involving the telecom industry, it is time to review and update the risk management plan. You have several key stakeholders working with you as you realize the importance of this plan in maintaining a competitive advantage.
One way you and your team are assessing the various risks that may impact the structure of the portfolio is to use:
A . Portfolio component charts
B . Portfolio reports
C . Weighted ranking and scoring techniques
D . Risk metrics
Answer: C