Your customer uses the ledger approach to multiple valuation. During conversion to SAP S/4HANA, which configurations will be required? Note: There are 2 correct answers to this question.
Your customer uses the ledger approach to multiple valuation. During conversion to SAP S/4HANA, which configurations will be required? Note: There are 2 correct answers to this question.
A . Convert all accounts of parallel valuations to reconciliation accounts
B. Assign accounting principles to all real and derived depreciation areas.
C. Define the document type for the accounting-principle-specific documents.
D. Configure delta depreciation areas to no longer post to the general ledger
Answer: A,B