If QM not started result recording what does the system do in response to a change in the

material quality……………..

A. Block the current inspection lot from processing

B. Create a new inspection lot with the different quantity

C. Cancel the current inspection lot and create a new one

D. Change the quality of the current inspection lot

Answer: A

Explanation:

In the SAP Quality Management module, if QM has not started result recording and there’s a change in the material quality, the system will A. Block the current inspection lot from processing. This ensures that no further actions are taken on the lot until the quality issue is addressed or the results are recorded.