You manage a project by using Project Standard 2013.
You need to use the Baseline2 fields to calculate Variance at Completion (VAC).You have already set Baseline2.What should you do?
A . Enter physical percent complete for the tasks that have actual values.Set the Baseline to the Baseline2, and reschedule uncompleted work based on the status date.
B . Change the Earned Value method to Baseline2 in the Task Information Form.Enter tracking data, and view the VAC on the Earned Value table.
C . Change the Baseline for Earned Value calculation option to Baseline2, and reschedule uncompleted work based on the status date.
D . Go to the Earned Value table and insert the Baseline2 column.Recalculate the project.
Answer: C