Your company uses Project Professional 2013.You are building a schedule by using predecessors to help determine a logical duration.The following image shows a baselined list of tasks with predecessors:
You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule.You need to determine what the results are to the schedule when inactivating Task C.How should you answer?
A . The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.
B . The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400.
C . The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.
D . The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.
E . The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged.
Answer: E