You are using a site survey tool for post-implementation validation. You have installed the appropriate adapter driver and imported a floor plan. Now, you want to take the next step in proper tool use. What must you do before gathering survey data after the floor plan is imported?

You are using a site survey tool for post-implementation validation. You have installed the appropriate adapter driver and imported a floor plan. Now, you want to take the next step in proper tool use. What must you do before gathering survey data after the floor plan is imported?
A . Install iPerf
B . Install WinPCAP
C . Calibrate the floor plan
D . Nothing, you can simply start capturing signal readings

Answer: C