You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a “team first” mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:
A . Any quality related error must be fixed only at the end to ensure that the deliverable is Done.
B. Iterative Product development, repetitive testing, and documentation help ensure quality is inherent in each Done deliverable.
C. Any quality requirement must consider the capacity and willingness of the organization to meet the business need.
D. The changing needs of the customers must be incorporated during the increments.
Answer: B