You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?

You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?
A . Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
B . With program execution
C . With program initiation
D . With program planning

Answer: A