You are a senior project manager, and your organization uses Project Standard 2013.You are managing a large ERP project with both part-time and full-time resources.The part-time resources have strict contractual limitations regarding working days and hourly availability.You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.What should you do?

You are a senior project manager, and your organization uses Project Standard 2013.You are managing a large ERP project with both part-time and full-time resources.The part-time resources have strict contractual limitations regarding working days and hourly availability.You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.What should you do?
A . Enter the availability start and end dates for each resource and change the percent of units to the agreed-upon amount in their contract.
B . Enter the availability start and end dates for each resource and change the working time for each resource to only include days and hours agreed upon in their contract.
C . Change the part-time resources’ tasks to manually scheduled to ensure the dates do not go past the agreed-upon terms of their contract.
D . Change the part-time resources’ units to the percentage they are available and set task constraints to must finish on to ensure the dates do not go past the agreed-upon terms of their contract.

Answer: B