You are a project manager who uses Project Professional 2013.You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode.What should you do?
A . For each new project, use the Status Bar to set new tasks to be auto scheduled.
B . Set the Default task type to Auto Scheduled for All New Projects in the Schedule Options.
C . For each new project, use the Auto Schedule button on the Tasks tab.
D . Set the New tasks created option to Auto Scheduled and set the Schedule Options to All New Projects.
E . Open the Global.mpt and use the Auto Schedule button on the Tasks tab.
Answer: D