Exam4Training

You are a project manager for a company that uses Project Professional 2013.You are developing a schedule and plan to use the leveling order of Priority, Standard.You need to create a task which leveling will not change.What should you do?

You are a project manager for a company that uses Project Professional 2013.You are developing a schedule and plan to use the leveling order of Priority, Standard.You need to create a task which leveling will not change.What should you do?
A . Set task priority to 1000.
B . Set task priority to 0.
C . Set task priority to 100.
D . Set task priority to 1.

Answer: A

Exit mobile version