You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
You are a NACE Level 2 Coating Inspector who has just arrived on a job in progress where there is no Inspection and Test Plan (ITP). The first morning you arrive the job is behind schedule and you are asked to take DIY Film Thickness readings.
Your FIRST preferred course of action is to:
A . Refuse to take readings until an is in place
B . Develop your own methodology and proceed take the readings
C . Use a generally accepted industry standard and to take readings
D . Call your supervisor
Answer: C