Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
A . Timelines of the sprint many differ dues to the workload
B. User Stories are in Ready state for only the first 2 to 3 sprints
C. Go-live scope is fixed on the first of January the following year
D. Project scope and planning are compelted and final
Answer: B