Workflow can be thought of as the Scrum Team’s policy for which of the following? (choose the best answer)
A . Defining when development is complete and validation begins.
B. How to get work done.
C. How to increase the Team’s WIP limit.
D. What completed work looks like.
Answer: B
Explanation:
This is similar to how the Definition of Done can be considered the team’s policies for what done looks like.