Within a MRP net requirements calculation, which of the following are demand elements? There are 3 correct answers to this question.

Within a MRP net requirements calculation, which of the following are demand elements? There are 3 correct answers to this question.
A . Sales order
B . Purchase order
C . On hand inventory
D . Planned independent requirements
E . Safety stock

Answer: A,D,E