With regard to project management, which of the following statements about project crashing Is true?

With regard to project management, which of the following statements about project crashing Is true?
A . It leads to an increase in risk and often results in rework.
B. It is an optimization technique where activities are performed in parallel rather than sequentially.
C. It involves a revaluation of project requirements and/or scope.
D. It is a compression technique in which resources are added so the project.

Answer: D