Why should the project team members be involved in the Identify Risk process?
The Identify Risk process determines the risks that affect the project and document their characteristics.
Why should the project team members be involved in the Identify Risk process?
A . They are the individuals that will most likely cause and respond to the risk events.
B . They are the individuals that will have the best responses for identified risks events within the project.
C . They are the individuals that are most affected by the risk events.
D . They are the individuals that will need a sense of ownership and responsibility for the risk events.
Answer: D
Explanation:
The project team members should be involved in the risk identification so that they will develop a sense of ownership and responsibility for the risk events and the associated risk responses.
Identify Risks is the process of determining which risks may affect the project. It also documents risks’ characteristics. The Identify Risks process is part of the Project Risk Management knowledge area. As
new risks may evolve or become known as the project progresses through its life cycle, Identify Risks is an iterative process. The process should involve the project team so that they can develop and maintain a sense of ownership and responsibility for the risks and associated risk response actions. Risk Register is the only output of this process.
Incorrect Answers:
A, B, C: These are not the valid answers for this question.
Latest CRISC Dumps Valid Version with 933 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund