Why might this be?

Yusef is a new procurement manager at FRD Incorporated. He is looking through the Risk Assessments for his department and notices that the cause of the risk is not identified.

Why might this be?
A . this is a mistake – all risk assessments should specify the cause of the risk. He should raise this with his manager
B. the organisation has a high risk appetite
C. the organisation has not recorded cause for cultural reasons
D. the organisation has completed the risk assessments incorrectly

Answer: C

Explanation:

This could be for cultural reasons within the company. P. 135 states that sometimes causes of risk are not recorded as this could lead to a blame culture within the company.