Exam4Training

Why is this a bad idea?

The Agile Release Train (ART) is near the end of the final Iteration of their first Program Increment. Integration into staging is more challenging than estimated. They add a week to the Innovation and Planning (IP) Iteration for integration and testing.

Why is this a bad idea?
A . Overall train velocity goes up and the time-to-market goes down
B . It substantially decreases the predictability of the Solution Intent
C . It reduces the overall predictability established through cadence and synchroniza-tion
D . It decreases job satisfaction by removing autonomy and purpose

Answer: C

Exit mobile version