Why is the Initiating a Project process used?

Why is the Initiating a Project process used?
A . To decide which project approach is suitable for the project
B . To fully understand how the project objectives will be achieved before committing significant resources
C . To produce the required Work Packages
D . To enable corporate or programme management to give authorization to deliver a project

Answer: B

Explanation:

The Initiating a Project process is used in PRINCE2 to ensure that there is a thorough understanding of how the project’s objectives will be achieved, which includes a definition of the project’s scope, benefits, risks, and approach before significant resources are committed. This process helps in establishing a clear and shared understanding of the project’s basis before moving forward.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources