Why is the executive’s decision to deliver the benefits early appropriate for managing the business case?
The executive has asked the project manager to plan for the ‘e-learning course’ to be used as soon as it is accredited. The aim is to start selling the ‘e-learning course’ while the remainder of the outputs relating to classroom-based delivery are finished. The sales of the ‘e-learning course’ will be entered into the business case.
Why is the executive’s decision to deliver the benefits early appropriate for managing the business case?
A . Because organizations with mature project management often include the early justification for the project in the business case.
B . Because the outputs being delivered incrementally will be beneficial and will allow the business case to be justified.
C . Because one of the PRINCE2 principles is that a project should focus on products to deliver the outputs early.
D . Because the business case should be updated after every increment of the ‘e-learning course’.
Answer: B