Why does the Product Owner want the Developers to adhere to its Definition of Done? (Choose the best answer)
A . To be able to reprimand the team when they do not meet their velocity goal for the Sprint.
B . To predict the team’s productivity over time.
C . To have complete transparency into what has been done at the end of each Sprint.
D . To know what the team will deliver over the next three Sprints.
Answer: C