Whose approval is needed to replace a Stage Plan with an Exception Plan?
Whose approval is needed to replace a Stage Plan with an Exception Plan?
A . Corporate or programme management
B . Project Board
C . Project Manager
D . Team Manager
Answer: B
Explanation:
The approval needed to replace a Stage Plan with an Exception Plan must come from the Project Board. This is because the Exception Plan is created when a Stage Plan is forecast to exceed its tolerance levels, and the Project Board is responsible for approving such significant changes in the project’s direction or management.
Reference: PRINCE2® Foundation official documentation and study materials.