Who starts the Daily Scrum?

Who starts the Daily Scrum?
A . The person coming in last. This encourages people to be on time and helps to stay within the time-box.
B . Whoever the Development Team decides should start.
C . The person who has the token.
D . The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.
E . The person who last broke the build.

Answer: B

Explanation:

According to the Scrum Guide1, during each Daily Scrum, each Developer answers three questions:

What did I do yesterday that helped meet our Sprint Goal?

What will I do today to help meet our Sprint Goal?

Do I see any impediment that prevents me or our Development Team from meeting our Sprint Goal? The Developers can select whatever structure and techniques they want, as long as their Daily Scrum focuses on progress toward achieving their Sprint Goal and producing a usable Increment. The Developers can start with any one person and proceed in any order.

Reference: Scrum Guide