Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
A . Corporate group
B . Project Board
C . Project Assurance
D . Executive

Answer: A

Explanation:

The information in a Lessons Report should be used by the corporate group to refine, change, and improve the standards within a quality management system. This approach ensures that insights and learnings gained from individual projects are integrated into organizational knowledge and contribute to continuous improvement across all projects.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources