Exam4Training

Who participates in the Inspect and Adapt event?

Who participates in the Inspect and Adapt event?
A . Only Product Management and Product Owners
B. Only Release and Solution Train Engineers
C. The entire Agile Release Train
D. Only stakeholders and Agile Team members

Answer: C

Explanation:

All ART stakeholders participate along with the Agile Teams in the I&A event. The result is a set of improvement backlog items that go into the Program Backlog for the next PI Planning event. In this way, every Agile Release Train (ART) improves every PI.

Latest SASM Dumps Valid Version with 185 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version