Who participates in the Inspect and Adapt event?
A . Only Product Management and Product Owners
B. Only Release and Solution Train Engineers
C. The entire Agile Release Train
D. Only stakeholders and Agile Team members
Answer: C
Explanation:
All ART stakeholders participate along with the Agile Teams in the I&A event. The result is a set of improvement backlog items that go into the Program Backlog for the next PI Planning event. In this way, every Agile Release Train (ART) improves every PI.