Who is the owner of the Product Backlog?
Who is the owner of the Product Backlog?
A . The Project Manager
B. The whole Scrum Team
C. The Scrum Master
D. The Product Owner
Answer: D
Explanation:
The Product Owner owns the Product Backlog and is accountable for it. There are no Project Managers in Scrum.
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments