Exam4Training

Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?

Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?
A . Project Assurance
B . Project Manager
C . Corporate or Programme Management
D . Project Support

Answer: A