Who is responsible for Definition of Done in Nexus?
A . Development Team Members
B. Scrum Master
C. Nexus Integration Team
D. Product Owner
Answer: C
Explanation:
The Nexus Integration Team is responsible for a definition of Done that can be applied to the Integrated Increment developed each Sprint.