Who is responsible for a sprint backlog item that contains several database tasks?
Who is responsible for a sprint backlog item that contains several database tasks?
A . The developers
B. Product owner
C. The company’s database specialist
D. Scrum master
Answer: A
Explanation:
Developers are responsible for conducting the work on the sprint backlog