Who has the overall responsibility for ensuring Nexus framework is understood and enacted by everyone?
Who has the overall responsibility for ensuring Nexus framework is understood and enacted by everyone?
A . Nexus Integration Team members
B. Product Owner
C. Scrum Master in the Nexus Integration Team
Answer: C
Explanation:
The Scrum Master in the Nexus Integration Team has overall responsibility for ensuring the Nexus framework is understood and enacted.