Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer.
A . Project Manager
B . Product Owner
C . Project Team
D . SCRUM Master
Answer: C
Latest C_ACTIVATE12 Dumps Valid Version with 198 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund