Who determines the tasks that are required to complete the committed backlog items in a sprint?

Who determines the tasks that are required to complete the committed backlog items in a sprint?
A . Scrum master
B . Product owner
C . Project manager
D . Project team

Answer: B

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments