Which workdays will be used?

A company uses Dynamics 365 Supply Chain Management.

The working time template is left blank when the period template is configured.

You need to determine the workdays that will be used in the inventory replenishment reporting.

Which workdays will be used?
A . calendar setup on the warehouse
B. system calendar for the country
C. 5-day work week
D. system date dimensions
E. 7-day work week

Answer: E

Explanation:

Calendar for a warehouse

You can assign a calendar to a warehouse to indicate the open dates for receiving and shipping. If no calendar has been assigned to a warehouse, it is assumed that it is open all days.

Reference: https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/supply-chain-calendars-master-planning

Latest MB-330 Dumps Valid Version with 198 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments