Exam4Training

Which work items should the BA prioritize with the remaining 16 hours of development capacity?

Universal Containers is implementing a Salesforce solution that’s designed to transform its customer service division. During sprint planning, it was determined that the development team would be able to successfully deliver all remaining work items.

However, due to unplanned delays, the development team is now at risk of being unable to complete the work items.

The project manager has asked for the business analyst’s (BA) help to prioritize the remaining work items. The development team has 16 hours of capacity remaining and is focused on launching a minimum viable product (MVP) of the customer service solution as soon as possible.

Which work items should the BA prioritize with the remaining 16 hours of development capacity?

US-4008 and US-4009
A . US-4008 and US-4009
B . US-4007 and US-4009
C . US-4009 and US-4010

Answer: B

Exit mobile version