The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two things should the project manager do? (Choose two)
A . Inform the customer that moving the milestone has a very high impact on project cost.
B . Escalate the Issue to senior management so they can impose a solution on the customer.
C . Convince the customer to keep the requirements as is and not move the milestone.
D . Review the customer’s priorities regarding the desired requirements for the milestones.
E . Discuss which requirements can be delivered faster with the project team.
Answer: B,C