An administrator needs to relocate an AHV cluster to a new datacenter during a maintenance window. The cluster will use the same IPs in the new datacenter.
Which two steps should be taken to prepare for this task? (Choose two.)
A . Stop all Nutanix Files clusters
B . Relocate the linked LDAP servers
C . Shut down all user VMs in the cluster
D . Reconfigure IPMI for the new datacenter
Answer: A C
Explanation:
Ref: https://next.nutanix.com/installation-configuration-23/physical-relocation-of-nutanix-clusters-38403