Which two steps are involved in this task?

Your company has recently decided to stop using the Fibre Channel Protocol (FCP) in the data center. You are asked to decommission FCP and reuse any UTA2 ports to 10 GbE.

Which two steps are involved in this task? (Choose two.)
A . Reboot the nodes.
B . Destroy any FC LIFs hosted on UTA2 ports.
C . Remove the FCP license from all nodes in the cluster.
D . License additional phttps://www.netapp.com/pdf.html?item=/media/13482-tr4375pdf.pdforts for 10 GbE connectivity.

Answer: CB

Latest NS0-162 Dumps Valid Version with 290 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments