Which two statements are correct when four teams are working on one single product?
Which two statements are correct when four teams are working on one single product?
A . There can be only one Product Owner.
B. There can be only one Product Backlog.
C. There can be 4 Product Owners.
D. There can be 4 Product Backlogs.
Answer: A,B
Explanation:
1 Product = 1 Product Owner, 1 Product Backlog