A project manager is working on the implementation of new phases in the production process of a regulated industry .
Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
A . Risk steering committee
B . Functional managers
C . Board of directors
D . Advisory team panel
E . Chief executive officer
Answer: B,C