A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin. You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents part of solution. NOTE: Each correct selection is worth one point.
A . Enter a value in the queue time after field for the painting operation
B . Make a resource group for each size and color and assign that group to the operation
C . Enter a value in the transit time on the painting operation
D . Enter a value in the queue time before field for the assembly operation
E . Build capabilities for each resource related to color
Answer: AD
Latest MB-320 Dumps Valid Version with 141 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund