Which TWO of the following statements are correct?

The PRINCE2 project management methodology has consistent principles governing roles, plans, processes and risks.

Which TWO of the following statements are correct?
A . Team plans are mandatory within PRINCE2.
B . A PRINCE2 organisation is a technical project team, assembled to achieve an unspecified objective.
C . A project issue is any factor which could have an effect on the project (either detrimental or beneficial).
D . One of the objectives of the process "Initiating a Project" is to define how the required product quality will be achieved.

Answer: C,D