Which two of the following are typical Daily Scrum outcomes?
Which two of the following are typical Daily Scrum outcomes?
A . The team is clear on the next steps toward the Sprint Goal.
B. The tasks are assigned to the developer.
C. Impediments identified by the Scrum Master.
D. A refined Daily Backlog.
Answer: A,C
Explanation:
There is no Daily Backlog. The team is self-organized.