Which two of the following are not correct about non-functional requirements?
Which two of the following are not correct about non-functional requirements?
A . The Project Manager takes care of non-functional requirements.
B. Non-functional requirements can be added to the Product Backlog.
C. Non-functional requirements are reflected in the Sprint Goal.
D. Non-functional requirements can be added to the Definition of Done.
Answer: A,C
Explanation:
Non-functional requirements are about the way functional features work, not about the goal for the Sprint. There are no Project Managers in Scrum.