Which two of the following apply during a project’s close out process? (Choose two.)
A . Communicate discrepancies to responsible parties.
B. Begin testing of installed infrastructure.
C. Evaluate the surroundings of the project and report back to the communications distribution professional of these findings.
D. Hire legal council for representation.
E. Create schedule for completion of punch list.
Answer: A,E