Exam4Training

Which TWO of the above mentioned characteristics relate to the phase test plan?

Topic 9, Scenario 9 "Test Management Documentation"

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing.

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a) Any deviation from the procedures described in the test

b) strategy document

c) The overall estimated costs, timescales and resource

d) requirements

e) A detailed schedule of testing activities

f) The development deliverables to be tested

g) Which test staff members (names) will be involved and when

h) Level of requirements coverage achieved

Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
A . a
B . b
C . c
D . d
E . e
F . f

Answer: C,E

Latest CTFL Dumps Valid Version with 219 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version