Which two network planning items should the SE determine prior to allocation hardware for the POC?

AN SE determines that a POC is necessary to overcome competitive FUD in an opportunity with an Enterprise account evaluating several HCI solutions. The customer will evaluate three

solutions in their datacenter simultaneously over the course of 4 days.

The customer schedules all necessary personnel to be available during this time.

Which two network planning items should the SE determine prior to allocation hardware for the POC? (Choose two)
A . VLAN tags
B . CVM and hypervisor IP address
C . TOR switch redundancy configuration
D . Switch port type
E . Source and number of cables

Answer: D,E