Exam4Training

Which two methods can be used to determine the status of the Switch/CTI Link between Avaya Aura® Communication Manager (CM) and Avaya Aura® Application Enablement Services (AES)? (Choose two.)

Which two methods can be used to determine the status of the Switch/CTI Link between Avaya Aura® Communication Manager (CM) and Avaya Aura® Application Enablement Services (AES)? (Choose two.)
A . Observe the AES Alarm Report.
B. Run an ASAI test on AES.
C. Observe the CM dashboard.
D. Observe the AES dashboard.
E. Run the status aesvcs cti-link command on CM.

Answer: B,E

Latest 72301X Dumps Valid Version with 95 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version