You deploy new server infrastructure by using a Cisco UCS platform.
Which two design options can you use to increase the redundancy of the new compute solution? (Choose two.)
A . a 10-Gb uplink port
B . a pin vNIC in the server profile to a specific Fabric Interconnect node that has failover disabled
C . adding multiple ports to uplink port channels
D . static pinning at the server ports
E . more than one server port to connect the Cisco UCS B-Series blade IOM
Answer: BC